The management team has asked you to reschedule the project so it finishes two weeks earlier without spending more money. They haven't removed any requirements from the project. Which technique would you use to shorten the project?

Select an answer:

fast-track

assign more experienced people to tasks on the critical path

crash the schedule

cut scope